L&T Green Reserve Construction Update: Towers 1–2 vs Towers 3–4
L&T Green Reserve has two UP-RERA registrations covering Towers 1–2 and Towers 3–4. Both carry a 28 May 2028 declared completion date. A fresh market update reports Towers 1–2 at basement-complete stage and Towers 3–4 at piling stage; HousingNetwork currently treats those exact construction-stage descriptions as awaiting primary confirmation.
Short answer
L&T Green Reserve in Sector 128, Noida is one buyer-facing project with two separate UP-RERA registrations covering different tower groups:
| Tower group | UP-RERA registration | Declared completion |
|---|---|---|
| Towers 1 and 2 | UPRERAPRJ459796/09/2025 | 28 May 2028 |
| Towers 3 and 4 | UPRERAPRJ794300/09/2025 | 28 May 2028 |
Both registrations name Larsen & Toubro Limited as the registered promoter.
For current construction progress, a fresh secondary market update reports Towers 1–2 with basement work completed and Towers 3–4 at the piling stage. HousingNetwork has not yet captured the latest primary quarterly UP-RERA construction filing that would independently verify those exact stage descriptions, so the current stage should be treated as market-reported / awaiting primary confirmation, not as an official HousingNetwork verification.
See the L&T Green Reserve project page for the broader project record, current price context, configurations, status and enquiry details.
Why the tower groups need to be tracked separately
Green Reserve is marketed as one project, but the statutory structure matters because Towers 1–2 and Towers 3–4 sit under different UP-RERA registrations.
That does not automatically mean buyers should think of them as different projects. It means the exact tower being purchased should be matched to the correct registration and its own statutory filings.
The current statutory mapping is:
- Towers 1–2 → UPRERAPRJ459796/09/2025
- Towers 3–4 → UPRERAPRJ794300/09/2025
Both records were registered on 2 September 2025 and both carry the same declared completion date of 28 May 2028.
That common completion date does not mean both tower groups must be at the same physical construction stage on every date. Different tower groups can progress at different speeds while remaining within the same broader declared timeline.
Current construction-stage signal
As checked on 11 October 2026, a fresh ReraTracker market update describes the two tower groups differently:
| Tower group | Current market-reported stage | HousingNetwork evidence state |
|---|---|---|
| Towers 1–2 | Basement work reported completed | Awaiting primary confirmation |
| Towers 3–4 | Piling work reported underway | Awaiting primary confirmation |
This distinction is useful because it gives buyers a more specific question to verify than a generic statement such as “construction is ongoing.”
However, HousingNetwork is deliberately keeping this stage information separate from the verified statutory facts.
The following are currently verified from the governed statutory record:
- two separate UP-RERA registrations;
- the tower-group split;
- Larsen & Toubro Limited as registered promoter;
- registration date of 2 September 2025 for both;
- declared completion date of 28 May 2028 for both.
The exact current physical stage above remains awaiting stronger primary evidence.
Does “basement complete” mean the structure is complete?
No.
If the market-reported Towers 1–2 stage is accurate, “basement work completed” describes a particular construction milestone. It should not be interpreted as confirmation that the superstructure, internal works, services, finishing, landscaping or possession readiness are complete.
Likewise, “piling underway” for Towers 3–4, if confirmed, describes an early structural/foundation-stage activity rather than an overall project-completion percentage.
Buyers should avoid converting a stage label into an assumed completion percentage unless the underlying engineer/architect/RERA filing actually provides that percentage and date.
Why HousingNetwork is not publishing a single project completion percentage
A single percentage can be misleading when different tower groups are registered separately and may be progressing at different physical stages.
For Green Reserve, the more useful buyer view is:
1. identify the selected tower;
2. identify the applicable UP-RERA registration;
3. check the latest dated progress filing for that registration;
4. compare the physical stage with the developer's construction communication;
5. keep the RERA-declared completion date separate from current site progress.
Until the latest primary progress filings are captured, HousingNetwork will not convert secondary stage signals into a project-wide “X% complete” claim.
What buyers should ask before booking
For a specific Green Reserve unit, ask for the latest written or portal-linked evidence for the exact tower being offered.
Useful checks include:
- Which tower is the unit in?
- Which UP-RERA registration applies to that tower?
- What is the date of the latest construction-progress filing?
- What stage does the latest engineer/architect certificate show?
- Does the developer's current construction update match the statutory filing?
- What is the current milestone-linked payment schedule for the selected unit?
- Has any tower-specific timeline changed?
- What does the agreement for sale state about possession and delay provisions?
This is more useful than relying only on a generic “under construction” label.
Do the two RERA registrations have different completion dates?
Based on the current governed statutory records, no.
Both Green Reserve registrations currently carry a declared completion date of 28 May 2028.
That date should be read as the RERA-declared completion date. It is not a HousingNetwork guarantee that every tower, fit-out item, amenity or possession process will necessarily complete on that exact date.
If a sales communication gives a different possession or handover expectation, compare that wording with the applicable registration and the buyer's governing documents.
For a detailed explanation of the two registrations, see L&T Green Reserve: What the Two UP-RERA Registrations Mean for Buyers.
How HousingNetwork will update this tracker
HousingNetwork will update this page when stronger dated evidence changes the current construction picture.
The evidence order is:
1. UP-RERA quarterly or statutory construction filings;
2. official L&T Realty project/construction updates;
3. credible dated secondary construction reporting;
4. market-reported signals, clearly labelled when not independently verified.
If stronger evidence later contradicts the current market-reported stage, the tracker will be corrected rather than preserving a stale construction claim.
Current buyer takeaway
The most important current distinction is not simply whether Green Reserve is “under construction.”
The project is split into two statutory tower groups, and a fresh market signal indicates that those groups may be at different physical stages.
What can be relied on today is the statutory structure and common 28 May 2028 declared completion date. The precise current construction-stage wording for each tower group remains a live evidence item and should be treated as awaiting primary confirmation until the latest statutory progress filings are captured.
For current price, configurations, project status and enquiry information, use the canonical L&T Green Reserve project page.
Related projects
Related insights
Sources & references
- L&T Realty — Green Reserve official project page (official)
Official project identity and buyer-facing Green Reserve context, including the two UP-RERA registrations. - ReraTracker — L&T Green Reserve construction update (secondary source)
Fresh secondary construction-stage signal reporting Towers 1–2 basement work completed and Towers 3–4 piling underway; treated as awaiting primary confirmation. - UP-RERA — Green Reserve Tower 1 and 2 (statutory record)
Statutory registration for Green Reserve Towers 1–2, promoter identity, registration date and 28 May 2028 declared completion. - UP-RERA — Green Reserve Tower 3 and 4 (statutory record)
Statutory registration for Green Reserve Towers 3–4, promoter identity, registration date and 28 May 2028 declared completion.
Considering a project?
Explore current HousingNetwork projects for verified facts, pricing context and RERA status.
About this article. This is independent editorial research published by HousingNetwork.in. It is not sponsored by, and does not represent, any developer, promoter or their authorised agent. Nothing here is financial, legal or tax advice — confirm project-specific facts on the relevant project page and independently verify material decisions before acting. See the Disclaimer and Terms.